ANKARA – KONYA HIGH-SPEED TRAIN PROJECT

Employer:
Main Contractor :
Project Location:
Project Description:

 

Within the scope of the project

Works Done:

Republic of Turkey State Railways (TCDD)

Mustafa Ozcan-Oztas Business Partnership

Konya

250 km/h high-speed railway infrastructure construction.

 

• 15.6 million m³ excavation
• 5.9 million m³ of fill
• 17 overpasses
• 25 underpasses
• 52 culverts
• 1 bridge
• 2,075 m tunnel
• 18,472 m wire fence

Images from Ankara Konya High Speed Train Project Works
Images from Ankara Konya High Speed Train Project Works
Images from Ankara Konya High Speed Train Project Works
Images from Ankara Konya High Speed Train Project Works

Türkiye – GEORGIA RAILWAY PROJECT

Employer:
Main Contractor :
Project Location:
Project Description:

General Directorate of Infrastructure Investments

Bayburt-Celikler Business Partnership

Kars-Ardahan

Earthworks, Engineering structures, Tunnel, Tunnel electricity and
construction of energy distribution center with electromechanical systems, station building, subballast, ballast and railway construction

TR-GRC Demiryolu Projesi Çalışma Görüntüleri
TR-GRC Railway Project Working Images
TR-GRC Railway Project Working Images

BURSA – YENİŞEHİR HIGH-SPEED TRAIN PROJECT

Employer:
Main Contractor :
Project Location:
Project Description:

TCDD General Directorate

Steels – YSE Business Partnership

Bursa

Earthworks, Engineering structures, Tunnel, Tunnel electricity and
construction of energy distribution center with electromechanical systems, station building,
subballast, ballast and railway construction

Bursa-Yenişehir High Speed Train Project
Bursa-Yenişehir High Speed Train Project

MERSİN – ADANA HIGH-SPEED TRAIN PROJECT

Employer:
Main Contractor :
Project Location:
Project Description:

TCDD General Directorate

Divers – Nuhoğlu – Transportation Partnership

Mersin-Adana

Earthworks, Engineering structures, bridge, underpass, overpass,
station building, sub-ballast, ballast and railway construction

Mersin Adana High Speed Train Project
Mersin Adana High Speed Train Project
dida-en-behyaz.png

Onur Mah. Turhan Cemal Beriker Blvd. Kiza Business Center A2 Block Floor: 1 No: 12 Seyhan/Adana

2025 DİDA ROAD CONSTRUCTION | ALL RIGHTS RESERVED. WEB: GRAPHIC DESIGN

If the road inspires confidence, Dida is behind it.

Otoyol Vektör Sanatı
bottom of page